Home

Rennstall Building update for June/July 2022

July 20, 2022

We are getting close to possession as the finishing touch's are being done for this luxury toy storage facility. Those blue doors really add a lot to the exterior of the building. ...

Read More

Rennstall Building Update for February/March 2022

March 8, 2022

- The last couple of months our crews have worked on the caretaker suite interiors.  - They have also started on the base preparation for the paving which will get laid at the end of March.  - The drywall mountin...

Read More

Rennstall Building Update for January 2022

January 26, 2022

Our crews are finishing up installing all exterior windows and doors as well as completing the roof.  They have started the electrical and mechanical rough-ins and will be starting to drywall this months as well.  Thi...

Read More

Rennstall Building Update for December 2021

December 10, 2021

Structural steel installs on the roof have been completed which means roofing is currently in full swing just in time before the winter snow starts falling.  Our crews are also currently installing the garage door panels a...

Read More

Rennstall Building update for November 2021

November 9, 2021

All insulated tilt-up concrete panels have been installed. Currently our crews are finishing up the structural steel for the roof and caretaker suite. Roofing will begin this month as well once the structural inspection is complete. ...

Read More

Get In Touch Today

Contact